Burn Rate
Definition
The rate at which a project is consuming its allocated budget, expressed as cost per unit of time (e.g., weekly or monthly). Tracking burn rate against the project plan reveals whether a project is on budget, ahead of schedule, or at risk of overrunning — enabling early corrective action.